Industries/Economy

Hightech Valley

Overview

  • Location The areas of Sandong-myeon and Haepyeong-myeon
  • Project period 2009 ~ 2020 (12 years)
  • Project cost KRW1.6868 trillion (Government subsidies : KRW51.9 billion)
  • Operator The Korea Water Resources Cooperation (K-water)
  • Attracting Business Electronic· information device, mechatronics, new material and carbon fiber, etc.

Project area size

표를 좌우로 이동하여 내용을 보실 수 있습니다.

Type Whole Industrial Land Residential Land Commercial· Support Land Land for Public Facilities
Whole 9,337,000㎡
(100%)
933.7 ha
5,180,000㎡
(55.5%)
518 ha
528,000㎡
(5.6%)
52.8 ha
242,000㎡
(2.6%)
24.2 ha
3,387,000㎡
(36.3%)
338.7 ha

Project Status & Plan

  • Proposal to establish a new industrial complex (Mayor of Gumi to the President): Mar. ‘08
  • Instruction to proceed (Ministry of Land, Transport, and Maritime Affairs): Aug. ‘08
  • Approval of the industrial complex plan and notification of topography drawing: Sep. ‘09
  • A consignment management contract for compensation (K-water and the City of Gumi): Sep. ‘10
  • First payment of land compensation (Donggok/Jeokrim, Sandong-myeon): Dec. ‘10
  • Second payment of land compensation (Dojung-ri, Sandong-myeon): Oct. ‘11
  • Construction of the 1st phase area (Sandong-myeon): Apr. ‘12
  • Announcement of compensation plan for the 2nd phase area (Haepyeong-myeon): Aug. ‘13
  • Cancellation of land permit area designation: Aug. ‘13
  • Notification of the change in the industrial complex plan: May ‘14
  • Notification of the change in the industrial complex plan: Jul. ‘17